MyWorldGo Beverage Can Making Machine Production Line Can Help You

Blog Information

  • Posted By : Gold Eagle
  • Posted On : Mar 11, 2021
  • Views : 159
  • Category : General
  • Description :   1. The rack installation of the Beverage Can Making Machine production line first starts with the head rack, and installs the middle rack of each section and the tail rack in sequence. Before installing the rack, first draw the center line over the entire length of the conveyor, and compare the center line to maintain the important conditions for the normal operation of the belt conveyor line in a straight line. When installing the racks, they must be aligned. The center line is also leveled with the shelf to the south. The error of the frame aligned with the center line is plus or minus 0.1 meter per meter of the captain, and the error of the conveyor to the center of the frame cannot exceed 35mm. After all the single sections are installed and aligned, the single sections can be connected.

Overview

  •   1. The rack installation of the Beverage Can Making Machine production line first starts with the head rack, and installs the middle rack of each section and the tail rack in sequence. Before installing the rack, first draw the center line over the entire length of the conveyor, and compare the center line to maintain the important conditions for the normal operation of the belt conveyor line in a straight line. When installing the racks, they must be aligned. The center line is also leveled with the shelf to the south. The error of the frame aligned with the center line is plus or minus 0.1 meter per meter of the captain, and the error of the conveyor to the center of the frame cannot exceed 35mm. After all the single sections are installed and aligned, the single sections can be connected.
      2. When installing the drive device, pay attention that the drive shaft of the belt conveyor line must be perpendicular to the center line of the belt conveyor line, so that the center of the width of the drive roller coincides with the center of the conveyor, and the axis of the reducer is parallel to the drive axis. All shafts and rollers are leveled accordingly, and the horizontal error of the shaft can be within the range of 0.5 to 1.5 according to the width of the conveyor. When installing the driving device, the installation of the tail wheel and other tensioning devices can also be carried out at the same time. The roller axis of the tensioning device should be perpendicular to the center line of the belt conveyor line.
    3. Install the rollers. After the frame, tensioning device and transmission device are installed, the roller racks of the upper and lower rollers can be installed, so that the conveyor belt has a curved arc that changes slowly, and the distance between the roller racks in the turning section is normal. 1/2~1/3 of the roller frame spacing. After the roller is installed, it should be able to rotate flexibly and briskly.
    4. In order to ensure that the conveyor belt always runs on the center line of the rollers and rollers, the following requirements must be met when installing the rack rollers, rollers and racks: all rollers are arranged in a row and parallel to each other; all rollers must Arrange in a row, parallel to each other, and keep horizontal; the supporting structure must be straight and keep horizontal.
      5. After the frame of the conveyor is fixed on the foundation or floor, the fixed belt conveyor line can be equipped with feeding and unloading devices.
      6. ​​When hanging the conveyor belt, first spread the conveyor belt strips on the idler rollers of the unloaded section, enclose the driving roller, and then spread them on the idler rollers of the heavy-duty section. The 0.5-1.5t hand winch can be used for hanging the belt. When tightening the belt to connect, the roller of the tensioning device should be moved to the limit position, and the trolley and the spiral tensioning device should be pulled toward the transmission device; and the vertical picking device should move the roller to the top . Before tightening the conveyor belt, the reducer and motor should be installed, and the braking device should be installed on the inclined conveyor.
      7. After the belt conveyor line is installed, an idling test machine is required. In the idling test machine, pay attention to the activity of the idler during the operation of the conveyor belt, the operating temperature of the driving part, no deviation, the activity of the idler during operation, the cleaning device, and the guide plate drive Part of the operating temperature, the tightness of the contact with the surface of the conveyor belt, etc., and the necessary adjustments must be made at the same time, and the load operation test machine can be carried out after all components are normal. If a screw-type tensioning device is used, the tightness must be adjusted again when the test machine is operated under load.

    If you want to purchase metal cap can making machinery production line, welcome you to send us messages at any time.